Decontamination work

Urstein landfill – Salzburg
Operational planning and transport of 550,000 tons of building residues
Disposition und Transport von 550.000 t Baurestmassen

Böhler Uddeholm – expansion Meerbusch – Düsseldorf part of the Meerbusch Strabag-Böhm consortium

Clearing, cleanup, and disposal of the pickling smut basins
Approx. ~ 140,000 tons excavating materials and contaminated sediments


Decontamination N54 of the “Ternitz landfill for pickling smut“ as part of the SB Ternitz consortium

Site facilities and operation’s planning; excavation, loading and transport of the contaminated excavation material; disposal of
~ 90,000 tons

Clearing the Grosswarasdorf tire landfill as part of the  AVE-Böhm consortium for clearing the tire landfill
Site facilities, planning of operation, loading, transport, and disposal/reuse of old tires amounting to
~ 2,500 tons

Dismantling of the Pilkington glass factory in Brunn/Gebirge as part of the Böhm-Saubermacher consortium

Demolition work, selective dismantling, disposal of demolition material, recycling of concrete, clay tiles, and asphalt, disposal of contaminated excavation material of ~ 150,000 tons

Decontamination work VCF – Vereinigte Chemische Fabriken as part of the Böhm-Saubermacher consortium

Decontamination work, building demolition, and surface cleaning

Clearing of the Recyclingpoint Blumau as part of the Recycling Point Blumau AVE-Böhm-ELA consortium
Site facilities, operation’s planning, sorting, loading, transport, and disposal of ~ 80,000 tons of waste

Clearing of the Fischerdeponie – Theresienfeld as part of the Böhm-Haider consortium

Site facilities, operation’s planning, loading, transport, and disposal of contaminated sediments/waste of
~ 1.6 million tons